North Oil Company (NOC) has awarded front end engineering design (FEED) contract to McDermott International for the Ruya Development, previously referred to as Al-Shaheen Phase 3-Batch 1, located offshore Qatar.

Al-Shaheen oil field is located in Qatari waters 80km north of Ras Laffan with facilities consisting of 33 platforms and more than 300+ wells. This is Qatar’s largest offshore oil field and one of the largest offshore oil fields in the world.​

According to a statement from McDermott, this is one of the largest FEED projects undertaken in McDermott’s history and follows the successful completion of the pre-FEED contract.

Scope of work includes developing FEED studies and deliverables suitable for an engineering, procurement, construction, installation and commissioning (EPCIC) project. This includes creating technical output data (FEED data), providing EPCIC schedule and cost estimates, and developing an early work plan for the brownfield scope with necessary site surveys.

source : https://www.oilandgasmiddleeast.com/